Delivering Refurbishment Works in a Live Aged Care Environment 

Delivering Refurbishment Works in a Live Aged Care Environment 

Refurbishment projects within aged care facilities require a unique approach. Beyond managing construction, project teams must prioritise resident wellbeing, operational continuity and careful stakeholder coordination to ensure works are delivered safely and with minimal disruption. 

Valen Project Services Director, Michael Hopwood, was involved in the refurbishment of vacant suites within the dementia ward of a Mark Moran Group aged care facility in La Perouse. 

Acting as the client’s representative throughout the project, Michael coordinated the design team, consultants and contractors, overseeing the project from early planning through to construction and completion. The refurbishment required careful planning, strict operational controls and close stakeholder collaboration to ensure works could be delivered safely within a live aged care environment. 

Project Overview 

Location: La Perouse, NSW 
Sector: Aged Care 

The project involved the refurbishment of vacant resident suites within the dementia ward, delivering modern, functional accommodation while maintaining the day-to-day operation of the facility. 

The scope required coordination of: 

  • Interior architects 
  • Aged care consultants 
  • Building stakeholders 
  • Head contractor 
  • Construction programming and staging 
  • Live environment management 

Planning for Success 

Early involvement was critical to the project’s success. 

Working closely with the client and consultant team, Michael coordinated the design process, programme development and pre-construction planning to ensure the project was ready for delivery. By identifying potential challenges early and resolving them before construction commenced, the team minimised delays and maintained programme certainty throughout the refurbishment. 

Delivering Works in a Sensitive Live Environment 

Construction within a dementia ward required a considered and carefully managed approach. 

All contractors completed comprehensive site inductions and adhered to strict safety protocols to protect residents, staff and visitors throughout the project. 

To further reduce disruption, the Head Contractor worked reduced hours to accommodate resident routines and daily activities. Construction sequencing was carefully planned to ensure works progressed efficiently while maintaining a safe, comfortable and operational environment for residents. 

Throughout the project, clear communication between the client, consultants, facility management and contractors ensured the refurbishment remained on programme while responding to the unique operational requirements of the facility. 

Delivering Better Outcomes Through Project Management 

Projects within healthcare and aged care environments require more than construction expertise. They demand proactive planning, stakeholder coordination and the ability to balance construction activities with the needs of people occupying the building. 

PROJECT DETAILS

PROJECT LOCATION

PROJECT VALUE

CLIENT

Related Articles

News & Info
Marion Cullimore

Partnering with Fiable since 2020

Our partnership with Fiable is about ensuring our clients have increased transparency and reduced risk when they are selecting their head contractors for their projects. The construction industry can have ups and downs, thin margins and fluctuating material costs and global supply chain pressures – one bad job can sink a contractor, leaving the client with a half-finished job, delays and the financial burden of getting the project completed.